Issue Number:DRB-204
Phase: Design
Decommissioning Process Dismantling PCV/RPV/Buildings
Investigation Subject Dismantling scenarios
Issue Establishing work sequence
Needs
① Establishing a dismantling work sequence
Time Axis: Dismantling PCV/RPV/Buildings [Long-Term 2]
Desired state and reasons for it
To dismantle PCV/RPV/building efficiently and effectively, it is desirable to establish specific dismantling work sequences based on dismantling scenarios and waste sorting strategies.
Current state against ideal
As part of the waste sorting strategy, waste streams are being investigated for solid waste in Government-led R&D Program on Decommissioning, Contaminated and Treated Water Management.
Issues to be resolved
It is difficult to investigate the work sequence of dismantling without a certain degree of progress in investigating dismantling scenarios for Issue No. DRB-203.
Relevant Issues
References
- DRB-204 (PDF)
- Overall Diagram (HTML, PDF)
- Overall Diagram (Detailed Version) (PDF)
- Download all diagrams (diagram_en.zip, 9.4 MB)
- List of issues
Please note that this English text is a provisional translation of the Japanese original.